OKC leaders are undecided about where to put a Bricktown entrance on a planned boulevard downtown.

By Clifton Adcock

The picture of the
boulevard that will replace the former Interstate 40 crosstown route has
become a little clearer in recent weeks, as the state Department of
Transportation made public presentations on the project.

Two
features of the street creating discussion are a western portion that
will be above grade at the level of the old I-40 and a section that will
go under the north-south railway.

A
third issue, however, has received little public attention: the
undecided route to Bricktown from the future major thoroughfare.

Although
current maps distributed by ODOT show direct access to Bricktown would
be created by extending Oklahoma Avenue south to intersect the
boulevard, no final decision has been reached. That plan would
necessitate the city purchasing the right of way from the owner of the
downtown U-Haul building on Oklahoma.

Instead,
the city is considering another options, too, said city Public Works
Director Eric Wenger: build the intersection at Compress Avenue, which
would create indirect access to Bricktown.

“The
one at Oklahoma [Avenue] is just a conceptual thing,” said ODOT
engineer Paul Green, who gave the updates to the MAPS 3 committee and
subcommittees. “The city is looking at that, actually. … The city does
not own the street right of way to connect through there.”

Green
said Compress Street is not the preferred alignment, but not owning the
right of way for Oklahoma Avenue complicates the matter.

“The
city is exploring their options,” Green said. “[ODOT’s] objective is to
build within our right of way. Now if the city has other wishes, we
will certainly try to accommodate those.”

Wenger said no decision has
been made on the route, so property owners have not been contacted. The
boulevard’s anticipated completion is in two years.

“We wouldn’t make contact until a decision was made and we’re still off a little ways,” he said.

He
said the Oklahoma Avenue option is favored, but it would require more
time and funding, whereas the Compress Street option would not be as
expensive and time-consuming since there is an existing street.

A decision likely will be made within the next six to eight weeks, Wenger said.

Room to grow

Green told the
subcommittees that ODOT planned to bring the boulevard further south of
the future convention center to give the building more room, and that
the street would go below grade east of S. E.K. Gaylord Boulevard to
allow streetcar and vehicular traffic to travel under the railway.

Transit subcommittee
members and Ward 2 Councilman Ed Shadid expressed concern that ODOT was
not working closely enough with the subcommittee or taking into account
the new preferred streetcar route, which calls for double track lanes on the boulevard.

ODOT’s objective is to build within our right of way.

—Paul Green

Having
the streetcar on the boulevard would require zones with no utility
lines. Moreover, the Intermodal Transit Hub study called for the
boulevard to remain below grade after passing under the railway,
allowing for potential high-speed and commuter rail.

Wenger said ODOT is consulting with the city on all these issues.

“There’s
a lot of planning we can do with ODOT at this point, making sure we
don’t put ourselves in a corner,” he told the council at its May 29
meeting. “But at the same time, we’ve got to wait for some of the other
consulting to occur so we know what we’re going to construct.”

Making the grade The plans also call for the boulevard to go above grade to pass over the com plicated intersection
of Reno, Classen and Western, a concept that concerned Shadid and Ward 4
Councilman Pete White, both in terms of slowing traffic and allowing
for development along the street.

“We’re
not trying to do what ODOT traditionally tries to do. We’re not trying
to move as many cars along that area as fast as we can. That’s not the
purpose; the purpose is exactly the opposite of that,” White said.

“If
you build it like an interstate high-way, even if you only build it a
couple hundred yards that way, you’ve defeated the whole purpose of why
we’re doing this, why we wanted a boulevard.”

Mayor
Mick Cornett said he has known for several years that the boulevard
would have to go above grade near that intersection, and that it would
help concentrate development.

“I
know it’s not necessarily been communicated throughout the community
because not everybody cares that much about a road that’s several years
away,” the mayor said.

Wenger
said keeping the boulevard at grade through that intersection would be
nearly impossible. The city and ODOT, he said, are reviewing options of
whether to build the above-grade section on columns or on an earthen
ramp.

“There is a
portion of the boulevard that will go over the top of those roads,”
Wenger said. “I think maybe that surprised some on [May 29], but it has
been that way for sometime.”